The City shall construct facilities to deliver recycled water to customers near the Water Pollution Control Facility.

Construction was completed on approximately eight miles of distribution pipelines in 2019, and on the recycled water tank, pump station, treatment facility in 2020. Phase 1 customer site retrofits and connections to the recycled water system were completed in 2020. Customer deliveries are scheduled to begin in 2021.